Jan De Nul expects to complete Anaklia Port dredging works within three weeks
Economy

Eric Bates
Ministry of Economy and Sustainable Development of Georgia
Jan De Nul expects to complete dredging works at the Anaklia Deep Sea Port within three weeks, while construction of the breakwater is ongoing, with more than 30% of the structure already completed, the company’s Project Director, Eric Bates, said on Tuesday.
“All operations in Anaklia are proceeding fully in accordance with the schedule. We have carried out significant dredging works in the access channel and turning basin. A total of 5.4 million cubic metres of sand has already been removed”, Bates said.
He noted that only a limited amount of work remained, primarily involving the final dredging of the access channel and turning basin.
“We expect to complete all dredging works within three weeks. At the same time, we are continuing construction of the breakwater, more than 30% of which has already been completed”, Bates said.
According to the Jan De Nul project director, construction of the breakwater has now moved into the water, and at the current pace, the structure is expected to be completed by the middle of next year.
“As a representative of Jan De Nul, I am pleased to be involved in the Anaklia Deep Sea Port project. Overall, I am satisfied with the progress of the works, as we began dredging in July 2026 and have already completed the bulk of the main works”, he concluded.